Question 1
You are using the maintenance planner to calculate the required software components for your SAP S4HANA conversion. What do you need to know regarding SUM?
Correct Answer: A
Question 2
What phases of SUM will be executed during an SAP S/4HANA conversion including DMO?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: C,D,E
Question 3
In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Question 4
Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?
Correct Answer: B
Question 5
You are performing an SAP S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of programs and other non-dictionary repository objects (SPAU)?
Please choose the correct answer.
Please choose the correct answer.
Correct Answer: C
Question 6
You are performing an SAP S/4HANA conversion with the migration repetition option. After which phase does SUM stop to enable a test cycle?
Correct Answer: A
Question 7
Which maintenance events are possible with SUM for an SAP system based on AS ABAP 7.40 and above? There are 3 correct answers to this question.
Correct Answer: A,C,D
Question 8
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,E
Question 9
You are performing an SAP S/4HANA conversion. When does the silent data migration (SDM) take place?