Question 1
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
Correct Answer: B
Question 2
How are earliest dates and latest dates of activities scheduled?
Correct Answer: B
Question 3
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
Correct Answer: B,D,E
Question 4
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
Correct Answer: D
Question 5
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
Correct Answer: C
Question 6
Resources
How are capacity requirements determined?
How are capacity requirements determined?
Correct Answer: C