SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 (C-TPLM22-67) Free Practice Test
Question 1
For which objects can billing plans be created? (2)
Correct Answer: B,E
Question 2
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Question 3
Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Question 4
Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Question 5
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 6
What are the three tables that are defined for order type in network costing?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 7
Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 8
Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 9
What does 'E' determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 10
What are the prerequisites for automatic requirements grouping on the top WBS element of a project?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D