PMI Portfolio Management Professional (PfMP) (PfMP) Free Practice Test

Question 1
A project manager reports that adding a dependency to a project may decrease the overall project cost. Other project managers raise concerns regarding changing portfolio dependencies.
How should the portfolio manager respond?

Correct Answer: A
Question 2
Assume you are preparing the first portfolio risk management plan for your outsourcing company, which typically handles call centers around the world. While the company has implemented portfolio management and has a Portfolio Oversight Group, it did not previously assess risks to the portfolio itself. Instead, it assumed risks would be managed at the project level. However, numerous customer complaints have been received. The root cause is once a new call center is established, limited if any planning is done as the manager rushes to have it ready and operational as soon as possible. This has led to a lack of understanding as to what is required for the call centers to be successful. In preparing this plan, you are reviewing the portfolio management plan because it:

Correct Answer: B
Question 3
You are the portfolio management for a big corporate with existence in 3 continents. While planning the performance management and in particular the dashboards and reporting tools, which of the following options is the most important to account for the different geographical locations?

Correct Answer: D
Question 4
Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:

Correct Answer: B
Question 5
You are managing a portfolio for a major car dealer in the region and due to diversity of locations, funding terms and your client's corporate structure, you have a big number of components to be included in the portfolio. With such a huge number, you need to prioritize the components in order to prepare the mix of components to execute. Where can you find the prioritization model?

Correct Answer: B
Question 6
Processes in the portfolio management layer interact with each others. For example, Manage Portfolio Information interacts with Provide Portfolio Oversight in order to store decisions made during the portfolio review meetings. Where are these decisions stored?

Correct Answer: D
Question 7
A new sponsor was appointed by the company in order to push more on the investments underway. The new sponsor wants detailed information on time and money and wants to get things done quickly. Which element of the portfolio management plan will be referred to for managing the sourcing of key resources?

Correct Answer: C
Question 8
Manage supply and demand comes down to balancing the requirements with what is available.
Resource requirements are a major input to the manage supply and demand process. Which of the following inputs to this process contains resource requirements?

Correct Answer: B
Question 9
As a portfolio manager you try to use all the information available to you in order to get the best out of the existing information and to better plan and manage the portfolio. The Enterprise Environmental Factors are important and referenced throughout the portfolio life cycle. Which of the following is correct regarding their purpose and focus?

Correct Answer: A
Question 10
A portfolio manager is working for an organization that has only loosely defined its goals and objectives. After interviewing several members of top management, the portfolio manager has a better sense of the organization's priorities.
In order to show how the portfolio components align with the perceived organizational priorities, the portfolio manager should create a portfolio:

Correct Answer: B
Question 11
Two functional managers within your portfolio are arguing about one scarce resource, and each one is claiming that the resource should be assigned to them. What should you do as a portfolio manager in order to solve this issue?

Correct Answer: D
Question 12
The portfolio management plan is intended to:

Correct Answer: D