Welcome to TestSimulate

Pass Your Next Certification Exam Fast!

Everything you need to prepare, learn & pass your certification exam easily.

365 days free updates. First attempt guaranteed success.

PMI Risk Management Professional (PMI-RMP) Free Practice Test

Question 1
During the project ' s lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 2
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Correct Answer: C
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 3
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 4
A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.
Which analysis should the risk manager perform to demonstrate this to the stakeholders ' ?

Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 5
A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team ' s tasks have yet to be completed.
What should the risk manager do next?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 6
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 7
The customer expresses concern about the increasing likelihood of delays from one of the subcontractors on the project. This risk was previously identified and planned for during the project planning phase. The project sponsor reassured the customer that this is a known risk and will be handled accordingly by the risk manager.
What should the risk manager do?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 8
A project manager has finished the project charter for a project and has now moved into the planning phase.
In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project ' s key stakeholders.
What is the first resource the project manager should reference?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 9
A financial services company has implemented a risk response plan to mitigate potential cybersecurity threats.
The project team has conducted a series of tests to ensure the new security measures are effective. However, some executives have expressed concerns about the impact of these measures on daily operations.
What should the risk manager do?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 10
Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 11
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?

Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 12
A global company with diverse teams is working on an extensive infrastructure project. The risk manager monitors separate risk registers for different project phases and identifies that several risks recorded during earlier phases are no longer applicable because the project has progressed into subsequent phases. The risk manager needs to control the risks that expired during the previous phases.
What should the risk manager do?

Correct Answer: C
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 13
A project team has just initiated a large project to move an organization ' s headquarters to another location.
The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 14
The scope of a large mobile network deployment project includes equipment to be furnished by the customer.
The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?

Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).