Question 1
Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.
What should the risk manager do next?
What should the risk manager do next?
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 2
A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a
10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.
Which analysis should the risk manager do to provide the project manager with the performance report?
10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.
Which analysis should the risk manager do to provide the project manager with the performance report?
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 3
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
Which technique should the risk manager use in this situation?
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 4
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
What should the risk manager do first to understand the impact on project cost?
Correct Answer: B
Question 5
While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?
Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 6
The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.
What should the risk manager do to enhance the project team ' s approach to risk reports?
What should the risk manager do to enhance the project team ' s approach to risk reports?
Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 7
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 8
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager ' s next step?
What should be the risk manager ' s next step?
Correct Answer: D