Microsoft Project 2010, Managing Projects (070-178) Free Practice Test

Question 1
You need to compare the total work of your project's deliverables against the baseline work. What should you do?

Correct Answer: D
Question 2
You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

Correct Answer: B
Question 3
You are reviewing the task details of your project. You receive the following warning message:
"This task has resources assigned which are over-allocated." You need to be able to identify a possible resolution for the over-allocated resources.
What should you do?

Correct Answer: C
Question 4
The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

Correct Answer: A,B
Question 5
You need to view the following information for your project: ?Current cost ?Baseline cost ?Actual cost ?Remaining cost ?Percentage of completion Which component will display the information?

Correct Answer: D
Question 6
You need to create a project plan in Project 2010 from a list of tasks in a Microsoft Access 2010 database. What should you do?

Correct Answer: C
Question 7
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?

Correct Answer: D