Question 1
APM, NR and other UPS products need to be derated at 30 degrees, and UPS5000-E does not need to be below 40 degrees.

Correct Answer: B
Question 2
What is the system efficiency of UPS5000-E?

Correct Answer: A
Question 3
The AI/DI port on the access control actuator supports to connect the ().

Correct Answer: C
Question 4
Regarding intelligent battery management in UPS5000-A, which of the following statements is correct? (Multiple choice)

Correct Answer: A,B,C,D
Question 5
UPS2000-G (6-20KVA) battery discharge time is significantly lower than the standard time, what may be caused by? (Multiple choice)

Correct Answer: A,B,C
Question 6
When the Huawei air-cooled air-conditioning compressor is turned on for the first time, the crankcase heating belt needs to be preheated for more than () hours.

Correct Answer: D
Question 7
A UPS system is configured with a single 50mm "2 (209A) cable, and the maximum current capacity allowed by the system is?

Correct Answer: B
Question 8
Which air supply mode requires reasonable raised floor height?

Correct Answer: B
Question 9
The device is connected to the ECC800 monitoring system through the smart ETH socket, using the () interface of the smart FTH socket.

Correct Answer: C