Question 1
In which of the following process groups is the project manager responsible for authorizing and applying organization resources to the subsequent project activities?

Correct Answer: A
Question 2
Which of the following are inputs of the perform quality assurance process?
Each correct answer represents a complete solution. Choose all that apply.

Correct Answer: A,B,D
Question 3
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Correct Answer: A
Question 4
You work as a project manager for PassGuide Inc. Your project was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?

Correct Answer: B
Question 5
Which of the following processes is described in the statement below?
"It is involved with many kinds of process design and with implementation and improvement to the IT infrastructure and service processes."

Correct Answer: B
Question 6
Which of the following types of organizational structures represents a hierarchy where every member has one leader and the employees are grouped by the area of expertise?

Correct Answer: D
Question 7
Which of the following are inputs of the Direct and Manage Project Execution process?
Each correct answer represents a complete solution. Choose all that apply.

Correct Answer: A,B,C
Question 8
You work as a project manager for PassGuide Inc. You want to reduce the affective conflicts at all levels, and also attain and maintain a reasonable amount of substantive conflict. Which of the following processes will you use to accomplish the above task?

Correct Answer: C
Question 9
Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?

Correct Answer: C