BICSI Registered Communications Distribution Designer (RCDD) (RCDDv14) Free Practice Test
Question 1
A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm's work product ensuring that the certified (mat documents are complete. In what capacity would the designer MOST LIKELY be serving?
Correct Answer: C
Question 2
The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?
Correct Answer: B
Question 3
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline What key elements should be included in the benefits register to achieve this goal?
Correct Answer: A
Question 4
A program receives initial approval from the selection committee to proceed with the program development.
What should the program manager do next"?
What should the program manager do next"?
Correct Answer: D
Question 5
Exhibit:

In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?

In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?
Correct Answer: D
Question 6
An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
How should the junior project manager respond to this request?
Correct Answer: B
Question 7
When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)
Correct Answer: A,B
Question 8
In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the work breakdown structure (WBS) During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
Correct Answer: B
Question 9
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule What should the program manager do?
Correct Answer: D
Question 10
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
Correct Answer: D
Question 11
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
What should the program manager do to ensure the success of the program?
Correct Answer: C
Question 12
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
Correct Answer: A,B
Question 13
A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?
What should the program manager do next?
Correct Answer: C