Question 1
Answer the following questions about the actions taken when preparing the Economic Case within the Full Business Case (FBC).

Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response that supports your decision.
Since approval of the OBC, there has been an attractive bid for the Old Fire Station Headquarters site by a supermarket company.
The bid is 15% higher than the original amount that the site was valued at.
Should the FBC production be delayed while the ranking of the options in the OBC is reassessed?

Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response that supports your decision.
Since approval of the OBC, there has been an attractive bid for the Old Fire Station Headquarters site by a supermarket company.
The bid is 15% higher than the original amount that the site was valued at.
Should the FBC production be delayed while the ranking of the options in the OBC is reassessed?
Correct Answer: A
Question 2
Scoping Solution 2: '20% increase in rate of participation, 75-85 education courses, 15-20% improvement in qualification success rate'.
Which 2 statements are correct about this entry in the Options Framework?
Which 2 statements are correct about this entry in the Options Framework?
Correct Answer: C,E
Question 3
Which is an appropriately defined SMART spending objective for greater learner success rates?
Correct Answer: D
Question 4
Pittville University insist that the business scope of the Pittville project should be based on the development of a new campus on the site of the Old Fire Station Headquarters.
Is this an appropriate application of the Five Case Model for this project?
Is this an appropriate application of the Five Case Model for this project?
Correct Answer: A
Question 5
Answer the following question about the Programme Business Case.
The following questions include only true statements, but only 2 statements are appropriate entries for that heading in the Strategic Case section.
Remember to select 2 answers to each question.
Which 2 statements should be recorded under the Existing arrangements heading?
The following questions include only true statements, but only 2 statements are appropriate entries for that heading in the Strategic Case section.
Remember to select 2 answers to each question.
Which 2 statements should be recorded under the Existing arrangements heading?
Correct Answer: C,E
Question 6
The Economic Case in the FBC has been completed and the Senior Responsible Owner, has asked that assurance of the investment decision be held for the project before the benefits realization plans are produced.
Should assurance of the investment decision be held at this point?
Should assurance of the investment decision be held at this point?
Correct Answer: C
Question 7
The Benefits Realization Framework section states:
1. It was identified in the OBC that existing schools and universities play a major role in the success or otherwise of the Pittville project. A strategy for Learning Provider engagement is to be prepared.
2. A senior manager within the Local Education Authority is ultimately responsible for benefits realization.
Which 2 statements apply to these entries?
1. It was identified in the OBC that existing schools and universities play a major role in the success or otherwise of the Pittville project. A strategy for Learning Provider engagement is to be prepared.
2. A senior manager within the Local Education Authority is ultimately responsible for benefits realization.
Which 2 statements apply to these entries?
Correct Answer: B,E
Question 8
Which detail should be explained in the Financial Case?
Correct Answer: D
Question 9
Using the Scenario, answer the following questions about roles and responsibilities on the Pittville project.
Which action should be completed by the sponsor for the Western Area Learning Improvements Programme?
Which action should be completed by the sponsor for the Western Area Learning Improvements Programme?
Correct Answer: D
Question 10
Using the Scenario, answer the following questions about scoping the proposal and preparing the Strategic Outline Case for the Pittville project.
Decide whether the approach is appropriate for stage 1, and select the response that supports your decision.
There is a risk that the local planning authority may reject proposals for development of the Old Fire Station Headquarters site. This will cause delays to the project.
Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?
Decide whether the approach is appropriate for stage 1, and select the response that supports your decision.
There is a risk that the local planning authority may reject proposals for development of the Old Fire Station Headquarters site. This will cause delays to the project.
Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?
Correct Answer: C