APM Project Fundamentals Qualification (PFQ) (APM-PFQ) Free Practice Test
Question 1
5 A. --> 5 B. --> 5D --> 5F
`-->4C. --> 4E --^
The total float of activity E in the above diagram is:
`-->4C. --> 4E --^
The total float of activity E in the above diagram is:
Correct Answer: D
Question 2
Which of the following statements about risks and issues is correct?
Correct Answer: A
Question 3
What is one of the main features of using analogous method of estimating?
Correct Answer: C
Question 4
A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.
Correct Answer: A
Question 5
The characteristics of a product that determine whether it meets certain requirements is known as the:
Correct Answer: A
Question 6
Which one of the following statements is true?
Correct Answer: C
Question 7
Which of the following statements refers to how scope is managed in a linear project but not an iterative project?
Correct Answer: C
Question 8
Which one of the following is the best description of project scope?
Correct Answer: A
Question 9
Which one of the following best describes a project issue?
Correct Answer: D
Question 10
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines, is referred to as the:
Correct Answer: A
Question 11
Which statement best describes a responsibility of the project manager:
Correct Answer: D
Question 12
In developing a network the first task after listing the activities is to...
Correct Answer: C
Question 13
What is the main objective of A. RAM?
Correct Answer: B
Question 14
Which one of the following statements is true?
Correct Answer: A
Question 15
What estimating method is most commonly used in the definition phase Of the project life cycle?
Correct Answer: C